Scope of Work.
The external and internal Refurbishment of a University Building. The Principal Contractors work included full external cladding replacement.
The access scaffolding was constructed to be fully independent from the building, no physical, mechanical ties or butt ties to the facade of the building.
Scaffolding work supplied included: –
- Access scaffolding to the perimeter of the building fully boarded at 2m lifts
- Stair Towers
- Long span bridges over low level roofs supporting eight fully boarded lifts
- Buttress and Kentledge
- Fully designed structure.